RICE Scoring

RICE scoring is a prioritization method that ranks projects by Reach times Impact times Confidence, divided by Effort. Intercom created it for its product roadmap: reach is people affected per period, impact is a 0.25 to 3 scale, confidence is 50%, 80% or 100%, and effort is person-months. A higher score means more impact per unit of work.

Related search rice scoringrice scoring modelrice framework

What is RICE scoring?

RICE scoring is a way to rank a list of projects by how much impact each one delivers for the work it takes. Each project gets four estimates, Reach, Impact, Confidence and Effort, combined into one number:

RICE score = (Reach x Impact x Confidence) / Effort

The method comes from Intercom. Sean McBride described it in a 2018 post on the Intercom blog after the team built its own scoring system “from first principles” to compare roadmap ideas that were otherwise hard to compare. The result, in his words, measures “total impact per time worked”.

What do the four RICE factors mean?

Intercom uses fixed scales for impact and confidence, so a team does not argue over whether something is a 7 or an 8.

FactorQuestion it answersHow it is measured (Intercom’s version)
ReachHow many people will this affect in a set period?A count, such as customers per quarter or transactions per month
ImpactHow much will it affect each person?3 massive, 2 high, 1 medium, 0.5 low, 0.25 minimal
ConfidenceHow sure are we of these estimates?100% high, 80% medium, 50% low; below that is a “moonshot”
EffortHow much work from everyone involved?Person-months, in whole numbers, with 0.5 for anything well under a month

Reach, impact and confidence are on top of the fraction because more of each is better. Effort is the divisor because more work is worse. Confidence exists to stop an exciting but unproven idea from beating a solid one: a project with big claims and no data gets cut in half.

A worked example from Intercom’s own numbers

McBride’s post gives the inputs for three example projects but not the final scores. Here they are worked through:

ProjectReach (per quarter)ImpactConfidenceEffort (person-months)RICE score
1. Change in the signup funnel450 customers3100%2450 x 3 x 1.0 / 2 = 675
2. Change to a widely used feature2,000 customers180%42,000 x 1 x 0.8 / 4 = 400
3. One-time change for existing customers800 customers250%1800 x 2 x 0.5 / 1 = 800

Project 3 ranks first despite the lowest confidence, because it takes a quarter of the effort of project 2. That is the kind of result RICE is meant to surface. McBride is also clear that the ranking is not a rule: a lower-scoring project may go first because another depends on it, or because some customers will not buy without it.

How can growth and marketing teams use RICE?

The formula works for any backlog where ideas compete for the same people’s time, including SEO pages, campaigns and experiments. Three adjustments make it fit:

  1. Define reach in your units. For a web page, visitors or searches per quarter. For an outbound play, accounts on the target list. For an onboarding email, new sign-ups per quarter.
  2. Keep impact tied to one goal. Pick the metric the quarter is judged on, such as qualified pipeline or trial-to-paid conversion, and rate impact against that only.
  3. Use smaller effort units if you need them. Many marketing projects take days, not months. Person-weeks work, as long as every project in the session uses the same unit.

Illustrative example. The company and numbers are fictional. A B2B software company’s growth team scores three ideas for next quarter:

IdeaReach (per quarter)ImpactConfidenceEffort (person-weeks)RICE score
Rewrite the pricing page6,000 visitors180%22,400
Five new comparison pages1,500 searches250%5300
Fix the demo request form on mobile2,500 visitors0.5100%0.52,500

The form fix and the pricing page rewrite beat the new content, mostly on effort and confidence. The comparison pages might still be the right long-term bet, and the team can choose to do them anyway, but now the trade-off is visible and someone has to argue for it. Tie the top-ranked projects to the quarter’s OKRs so the impact scores mean the same thing to everyone.

RICE compared with other prioritization methods

MethodHow it worksBest forWeakness
RICE(Reach x Impact x Confidence) / EffortRanking a mixed backlog with different audience sizesNeeds a reach estimate for every idea
ICEImpact, Confidence and Ease, each usually 1 to 10Scoring many small growth experiments quicklyNo separate reach, so a niche idea can outscore a broad one
Value vs effortPlot each idea on a 2x2 gridA fast visual in a planning meetingMerges reach and impact into one guess
MoSCoWMust, should, could, won’tDeciding scope for a fixed releaseDoes not rank items within a category

What are the common RICE mistakes?

  • Using a 1 to 10 scale for reach. Reach is a count. Turning it into a rating removes the difference between a change that affects 50 people and one that affects 5,000.
  • Mixing units. Weeks for some projects and months for others make the scores incomparable.
  • Generous confidence. If the estimate is a guess, it is 50%. Scoring everything at 80% or above turns the factor off.
  • Treating the score as the decision. It is an input. Dependencies, strategy and deals that need a feature still matter, and Intercom’s own guidance says to work “out of order” when there is a reason.

RICE fits naturally into a growth marketing process, where a team runs a steady flow of experiments and needs a consistent way to choose the next one. For product teams, it pairs well with a product-led growth model, where reach can be read straight from product analytics instead of estimated.

Common questions about RICE Scoring

How do you calculate a RICE score?

Multiply reach by impact by confidence, then divide by effort: RICE = (Reach x Impact x Confidence) / Effort. Write confidence as a decimal. A project that reaches 2,000 customers a quarter, with medium impact (1), 80% confidence and 4 person-months of effort, scores 2,000 x 1 x 0.8 / 4 = 400.

What do RICE scores mean?

A RICE score estimates impact per unit of work, in the units you chose, such as customers affected per quarter for each person-month. The number means little on its own. It is useful only for comparing projects scored by the same team with the same units in the same session: sort the list and the top of it is where to look first.

What is the RICE scale?

Intercom's original scales are: impact 3 for massive, 2 for high, 1 for medium, 0.5 for low and 0.25 for minimal; confidence 100% for high, 80% for medium and 50% for low, with anything lower treated as a moonshot; and effort in whole person-months, with 0.5 for anything well under a month. Reach is a raw count of people or events per period, not a scale.

What is the difference between RICE and ICE scoring?

ICE scores impact, confidence and ease, usually each on a 1 to 10 scale, and multiplies or averages them. RICE adds reach as a separate count and measures effort in person-months instead of an ease rating. RICE takes longer but separates how many people a change affects from how much it affects each one. ICE is quicker for scoring many small growth experiments.

Can marketing and growth teams use RICE?

Yes. Define reach in marketing units, such as visitors to a page per quarter or accounts on a target list, keep Intercom's impact and confidence scales, and measure effort in person-weeks if most projects are smaller than a month. Score SEO pages, campaigns and experiments in the same session so the units match.